【单选题】

The project team is responsible for creating 10,000 small parts. Basing the quality of the batch on an intensive review of 500 parts is an example of what quality control tool?

A.
Quality audit
B.
Pareto principle
C.
Statistical sampling
D.
Inspection
举报
参考答案:
参考解析:
.
刷刷题刷刷变学霸
举一反三

【单选题】All of the following are common results of risk management EXCEPT?

A.
Contract terms and conditions are created.
B.
The project management plan is changed.
C.
The communications management plan is changed.
D.
The project charter is changed.

【单选题】In organizing a project, a project manager must deal with conflict. Which statement is true regarding conflict in projects?

A.
A matrix form of organization can produce a lack of clear role definitions and lead
B.
Sources of conflict include project priorities, PERT/CPM schedules, Administer Procurements procedures, and type of contract.
C.
Conflict is to be avoided whenever possible.
D.
Strong matrix project managers have few human resource conflicts, because they can dictate their needs to functional managers.

【单选题】Which of the following options describes contingency reserve?

A.
Budget reserved for unplanned changes to project scope and cost.
B.
Budget reserved for covering poor performance.
C.
Budget reserved for unplanned but potential required changes that can result from realized risks identified in the risk register.
D.
Budget reserved for covering cost overrun due to approved changes.

【单选题】What does a resource program represent?

A.
Expected resource using status according the time periods
B.
Expected resource requirement of actions in critical path
C.
resource allocating status of WBS
D.
resource allocating status for actions

【单选题】A control chart helps the project manager:

A.
focus on the most critical issues to improve quality.
B.
focus on stimulating thinking.
C.
explore a desired future outcome.
D.
determine if a process is functioning within set limits.