【单选题】

In your project,you have identifed important risks,and planned appropriate responses to the risks.Some risks e.g. possibility of natural disasters has been documented and accepted in your risk management plan.If there are risks that remain after you have taken these steps,then such risks are called______.

A.
unidentifiable risks
B.
residual risks
C.
secondary risks
D.
accepted risks
举报
参考答案:
参考解析:
.
刷刷题刷刷变学霸
举一反三

【单选题】You are an expert in risk management,having worked in the field for more than 15 years.Your project is behind schedule and in your project.you are in the process of identifying which risks may affect ...

A.
mention to your sponsor that since you are an expert in risk management, there is no need to do qualitative risk management and the team can directly go to quantitative risk management phasThis will also save time since your project is behind schedule
B.
agree with your sponsor that not doing qualitative risk analysis may mean some risks will remain unidentified and increase the probability of failure in your project
C.
mention to the sponsor that usually in your past experience,qualitative risk analysis was a waste of time and not recommended for this project
D.
mention to the sponsor that this is a type of project where qualitative risk analysis is not requireSpecific categories of projects do not need qualitative risk analysis

【单选题】The probability of failure for a project element is often called exposure to risk,or risk exposure.This exposure may be mitigated by taking measure to avoid a particular approach or use of specific te...

A.
conduct further studies and analysis until a more attractive alternative is found
B.
disregard the exposure to risk because nothing can be done
C.
not performs the activities with risk exposure and save the money which would have been spent on them
D.
establish a contingency plan to overcome any adverse activitwhich may include a contingency allowance