Managing risks and documenting them is very important in project planning process.You are in the process of defining key risks,including constraints and assumptions,and planned responses and contingencies(where appropriate).These details will be included in the______(choose the best answer).

A.
project management plan
B.
project baseline
C.
risk response plan
D.
risk baseline
举报
参考答案:
参考解析:
.
刷刷题刷刷变学霸
举一反三

【单选题】43(). A.earth B.grass C.water D.ice

A.
The lake lay before me, blue and peaceful, in the evening (36) . On either side the mountains rose sharply surrounding it in a kind of bowl. A few sheep (37) their sides here and there and a cow was (38) with eating on the lower slopes. The place was so far away, so untouched by human work that it seemed the very place to (39) . Even Higgs, I thought, won’t be able to find me here.
B.
I sat down by the edge of the lake, and pulled (40) my shoes and socks, put my (41) in the water. It was cold, like ice. After a moment I (42) over and spread some of the (43) on my hot face. I could see myself faintly in the water staring at me like a (44) .
C.
I realized suddenly how (45) I was of running away. Surely, I thought I could live here for a few days, out of (46) of Higgs and his men. While I tried to (47) some plans for the future, I found a tiny cottage on the far side of the (48) with some smoke coming from its roof. I still had a little money. Perhaps they would give me a (49) and some food.
D.
As I watched, a man came out of the house and down to a little (50) at the lakeside. He got into it and began to move (51) towards my side. I could not see his (52) at first. He continued calmly (53) the lake, and when he was about halfway, he rested his oars and the boat drifted into a patch of sunlight. He (54) a hand in a friendly way of greeting. I Was about to raise mine, (55) all at once, I saw his face clearly, it was Higgs!