【单选题】
Project team A has been hired to manage a transportation project very similar to dozens at projects they’ve managed successfully in the past.The team had determined that the probability of achieving project objectives is 94%.The team has determined the size of contingency reserves that may be needed.These determinations are included in which process
参考答案:
参考解析:
举一反三