logo - 刷刷题
下载APP
【单选题】

For what are flow charts primarily used?

A.
Schedule management
B.
Improving stakeholder communication
C.
Quality measurement tool
D.
Risk management tool
举报
参考答案:
参考解析:
.
刷刷题刷刷变学霸
举一反三

【单选题】In planning your project, which would generally have the highest priority; quality, cost or schedule?

A.
Cost is most important, quality next, and then schedule.
B.
Quality is more important than cost or schedule.
C.
Schedule is most important, quality next, and then cost.
D.
It should be decided for each project.

【单选题】What is the goal of a quality audit on a project?

A.
Deliver higher quality products for the same price.
B.
Rate the quality of a process
C.
Identify inefficient and ineffective processes.
D.
Report project quality to the sponsor.

【单选题】A schedule performance index of less than 1.0 indicates that the

A.
Project is running behind the monetary value of the work it planned to accomplish
B.
Earned value physically accomplished thus far is 100%
C.
Project has experienced a permanent loss of time
D.
Project may not be on schedule, but the project manager need not be concerned 正确答案:A

【单选题】Your cost forecast shows that you will have a cost overrun at the end of the project.

A.
Eliminate risks in estimates and re-estimate.
B.
Meet with the sponsor to find out what work can be done sooner.
C.
Cut quantity.
D.
Decrease scope.

【单选题】What is the duration of a milestone?

A.
Shorter than the duration of the longest activity
B.
Shorter than the activity it represents
C.
There is no duration
D.
Same length as the activity it represents

【单选题】While creating the project charter, a key stakeholder does not offer any input. The project manager repeatedly asks the stakeholder to provide the necessary input to complete the high-level requiremen...

A.
Remove the stakeholder from the stakeholder list
B.
Assume the requirements together with the project team
C.
Add the missing input as a risk to the high-level risk description
D.
Escalate the issue to the project sponsor