logo - 刷刷题
下载APP
【单选题】

A project team is collecting all the requirements and scope from the customer and stakeholders. The project manager in charge of this project is trying to complete the charter. What tool and technique should the project manager use?

A.
Scope decomposition
B.
Expert judgment
C.
Activity sequencing
D.
Project scheduling
举报
参考答案:
参考解析:
.
刷刷题刷刷变学霸
举一反三

【单选题】A high performing project is almost in the completion stage when the sponsor requests a minor change. What should the project manager do first?

A.
Deny the request
B.
Refer to the management to decide
C.
Allow the team to handle
D.
Explore, clarify, and define the problem

【单选题】Project change control is part of which of the following plans?

A.
Quality management
B.
Risk management
C.
Configuration management
D.
Communication management

【单选题】As of the fourth month on the Acme project, cumulative planned expenditures were ¥100,000. Actual expenditures totaled ¥120,000. How is the Acme project doing?

A.
It is ahead of schedule.
B.
It is in trouble because of a cost overrun.
C.
It will finish within the original budget.
D.
The information is insufficient to make an assessment.

【单选题】Which tool assists the project manager in executing large and complex projects more efficiently?

A.
Project management knowledge database
B.
Organization process asset
C.
Project management information system
D.
Lessons learned