A project team is collecting all the requirements and scope from the customer and stakeholders. The project manager in charge of this project is trying to complete the charter. What tool and technique should the project manager use?
A.
Scope decomposition
B.
Expert judgment
C.
Activity sequencing
D.
Project scheduling
举报
参考答案:
参考解析:
刷刷题刷刷变学霸
举一反三
【单选题】A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for 2 percent spillage, mounting to over two t...
A.
Quality management plan
B.
Quality policy
C.
Control charts
D.
Project management plan
查看完整题目与答案
【单选题】A high performing project is almost in the completion stage when the sponsor requests a minor change. What should the project manager do first?
A.
Deny the request
B.
Refer to the management to decide
C.
Allow the team to handle
D.
Explore, clarify, and define the problem
查看完整题目与答案
【单选题】Project change control is part of which of the following plans?
A.
Quality management
B.
Risk management
C.
Configuration management
D.
Communication management
查看完整题目与答案
【单选题】As of the fourth month on the Acme project, cumulative planned expenditures were ¥100,000. Actual expenditures totaled ¥120,000. How is the Acme project doing?
A.
It is ahead of schedule.
B.
It is in trouble because of a cost overrun.
C.
It will finish within the original budget.
D.
The information is insufficient to make an assessment.
查看完整题目与答案
【单选题】Project manager completes the project scope statement. In addition to the organizational policies that will impact the project, what should the project manager do next?
A.
Create a work breakdown structure
B.
Define project deliverable
C.
Develop a communications plan
D.
Create a project charter
查看完整题目与答案
【单选题】You are asked to select tools and techniques to implement a quality assurance program to supplement control quality. Which of the following would you choose?
A.
Quality audits
B.
Statistical sampling
C.
Pareto charts
D.
Trend analysis
查看完整题目与答案
【单选题】A product is test launched. The customer reports a few issues.The cost of correcting these issues is classified as which of the following?
A.
Prevention
B.
Repair
C.
nternational (Internal) failure
D.
External failure
查看完整题目与答案
【单选题】During testing, many projects are identified. The project manager would like to analyze the root causes of these defects.The project manager should use which of the following tools?
A.
Scatter diagram
B.
Pareto chart
C.
Ishikawa diagram
D.
Run chart
查看完整题目与答案
【单选题】Which tool assists the project manager in executing large and complex projects more efficiently?
A.
Project management knowledge database
B.
Organization process asset
C.
Project management information system
D.
Lessons learned
查看完整题目与答案
【单选题】A project has an SPI1. The project manager should take which of the following corrective actions?
A.
Crashing
B.
Fast tracking
C.
Resource leveling
D.
Monte Carlo analysis
查看完整题目与答案